Experience
Metrod, KlangMALAYSIA
Copper Hot Rolling Mill Design and Fabrication
- COMPLETED –
MARCH 2016
- DURATION –
6 MONTHS
- CLIENT –
METROD
SCOPE OF WORK
- Detailed measurement and replication of Copper Rolling Mill machine
- 3D assembly drawings
- 300 complete fabrication drawings of individual parts
Component Detailed Drawings // Full 3d Assembly // Fabrication Drawings // Fabrication Support
SabahMALAYSIA
FLNG Project
- COMPLETED –
DECEMBER 2015
- DURATION –
7 MONTHS
- CLIENT –
KROHNE OIL AND GAS
SCOPE OF WORK
- Detailed design of 5 non standard skids for FLNG platforms
- 3D assembly drawings
- In depth design optimisations within safety limits
Detailed Engineering Design // STAAD.Pro Software Design and Analysis // Intergraph Caesar II Stress Analysis // Fabrication Drawings // Fabrication Support // Fabrication Inspection and Integrity Assessment
FSO Gagak Rimang, Banyu UripINDONESIA
Banyu Urip Export Facilities Project
- COMPLETED –
JANUARY 2015
- DURATION –
38 MONTHS
- CLIENT –
PT REKAYASA ENGINEERING EXXON MOBIL
SCOPE OF WORK
- Mooring tower at 33 water depth
- 20 inch / 23 km offshore pipeline
- Detailed designed & installation Engineering of the 20” offshore pipeline
Project Management // Detailed Design & Installation Engineering of the 20” Offshore Pipeline // ABAQUS Finite Element Analysis (FEA) for pipeline crossings // ABAQUS Finite Element Analysis (FEA) for HT (High Temperature) pipeline lateral buckling // ABAQUS Finite Element Analysis (FEA) for ET Subsea Riser & Tie-In Spool Analysis considering Platform Movement due-to Seismic Activity // Pipeline Process Engineering & Surge Analysis from Storage Tank Farm (EPC 1) to the FSO (EPC 4) Inlet using program OLGA & PVT Simulator // Structural Engineering Support Service for Mooring Tower Engineering & Fabrication // Procurement Support // Engineering Fabrication // QA QC for the EPC3 & Contract Management
COLOMBO PORTSRI LANKA
Colombo Port Offloading Facilities
Integrity Assessment Project
- COMPLETED –
DECEMBER 2014
- DURATION –
7 MONTHS
- CLIENT –
CHEVRON
SCOPE OF WORK
- Cathodic protection assessment and installation
- 10 inch / 640 meter pipeline
- 15 years design life
Inspection And Verification Of Pipeline Wall Thickness // Procurement // Supply Installation Supervision // Testing And Commissioning Of The Cathodic Protection Sacrificial Anode
Al Basrah & Khor Al Amaya Oil Terminals IRAQ
Iraq Crude Oil Export Expansion Project (ICOEEP) Phase 1
- COMPLETED –
SEPTEMBER 2012
- DURATION –
24 MONTHS
- CLIENT –
IRAQ SOUTH OIL COMPANY
SCOPE OF WORK
- Two 48 Inch Pipelines
- A Third Pipeline Shore Approach Section
- Spur Pipeline
- Three SPMs
Engineering Management // Detailed Engineering Design of the Pipelines and Subsea Structures // Shore Approach Design // Trenching / Backfilling Design // Tie-in / Expansion Spool Design // Hanger / Tie-in Flange Design // Dropped Object Study // Subsea Valve Manifold Structural Design // Material Take-Off // Pipeline Operation and Maintenance Philosophy // Specifications // Drawings // J-Tube Design // Procurement Support Services (Technical Support) // Pipeline / Subsea Structure // Final Design Report // Pipeline/SPM/PLEM/SSVM Installation Engineering
Dar Es SalaamTANZANIA
Tanzania SPM Replacement Project
- COMPLETED –
MARCH 2012
- DURATION –
20 MONTHS
- CLIENT –
TANZANIA PORTS AUTHORITY
SCOPE OF WORK
Ofnir designed and developed an offshore terminal for the import of crude oil and white products capable of mooring tankers in the range of 40KDWT to 150 KDWT including;
- 28 inch / 4.5 km crude pipeline
- 24 inch / 4 km white product pipeline
Engineering Management // Design Basis Memorandum // Pipeline Detail Design // Shore Approach Design and Determined Burial Depth Requirement at the Surf Zone // (MTO) Material Take-Off // Cathodic Protection System Design for Pipeline // Interface with Certifying Authorities // Mechanical Protection / Trenching // Estimated Pipeline Thermal Expansion and Requirements for Expansion Absorbing Devices or Thrust Blocks // Expansion Offset Sizing // Final PLEM Arrangement // Final Design Report
Ofnir Engineering
Work Experience